  • Project description:

    Improvements for this project will generally include installing a new soldier pile wall to restore support to the roadway. Work will also include grading of the Nicasio Creek bank below, a new guardrail and rehabilitation of the adjacent underground culvert that crosses below Lucas Valley Road.

  • Delivery address:
    Hugh Davis
    3501 Civic Center Drive
    San Rafael , CA 94903

Key dates

  • Issue date: Monday, July 7, 2025
  • Submission due by: Thursday, July 24, 2025, 2:00 pm
  • Question submittal date: Monday, July 14, 2025, 5:00 pm

Additional information

  • Proposal number: 2024-19
  • Project information:

    Improvements for this project will generally include installing a new soldier pile wall to restore support to the roadway. Work will also include grading of the Nicasio Creek bank below, a new guardrail and rehabilitation of the adjacent underground culvert that crosses below Lucas Valley Road.

  • Attachments:

    The documents in this list may not work with all assistive technology and are being remediated. For alternative formats, please email Hugh Davis or phone 415-473-4232. To use the California relay service, dial 711.

    • LUCAS VALLEY ROAD MP 8.02 RETAINING WALL AND CULVERT REPAIR (0.19 MB) — Improvements for this project will generally include installing a new soldier pile wall to restore support to the roadway. Work will also include grading of the Nicasio Creek bank below, a new guardrail and rehabilitation of the adjacent underground culvert that crosses below Lucas Valley Road. The Engineer’s estimate for this project is $700,000. Bids are required for the entire work described herein.The Contractor shall possess a valid Class “A” License at time of bid submittal.
  • Location:
    ,
  • Mandatory walkthrough:

    An optional pre-bid zoom conference call is scheduled for 9:30 a.m. on Friday, July 11, 2025
    and optional pre-bid site walk is scheduled at 1:00 pm on Friday July 11, 2025 at the site.
    Contractors are not required to attend these meetings in order to submit a qualified bid.